Soma has experience in executing complex projects in nearly all states within India, and is actively exploring projects in various other geographies including Africa, Middle East, South East Asia and Eastern Europe.
Soma undertakes projects as a construction service provider (EPC Contracts) as well as a infrastructure developer (PPP Contracts). Soma has a long history of successfully executing projects in partnership with large international and domestic construction companies.
Soma has long-standing relationships with various clients that include the largest government agencies implementing various core infrastructure projects for the nation. Soma also has excellent relationships with various financial institutions, investors, and partners.
ISO 9001
ISO 14001
ISO 45001
The National Highway (NH9) project in Vijayawada city on EPC basis comprises of 4 lane road of length of 5.122 Km including 6 lane elevated flyover of length 2.550 M, 3 VUPs, 1 PUP.
The National Highway (NH1) project in Panipat - Jalandhar Section on DBFO Pattern (BOT) under NHDP Phase-V comprises of construction of 6 laning of 291.10 Kms including 10 Major Bridges, 72 flyovers, 5 Viaducts and CD Works.
The Subansiri Lower Hydro Electric Project (2000 MW) consists of 127 M high & 283 M length Concrete Gravity Dam on Subansiri River with 9 Spillways. River diversion is planned by construction of 5 nos of diversion tunnels of 9.5 M dia, each of 600 M average length.
The project involves Construction of RCC (Roller Compacted Concrete) Dam across Vaitarna River under Water Supply Project package MVP–1, MCGM, Mumbai. The Dam is 102.40 M High, 573 M Long and 90 M Wide. It is Second Largest RCC Dam in India and is the 9th quickest to be built as per ICOLD Certification.
The project involves of Tunnel having finished dia of 5.5 M and length of 6.657 Km using Tunnel Boring machine (TBM) from Gundovli to Kapurbawdi under package MVP–16, MCGM, Mumbai. The scope includes construction of Inlet shaft & Outlet Shaft having finished dia of 11.00 M and depth 112.035 M.
The Metro Project (package BC-16) of Phase-II of Delhi MRTS comprises of construction of Twin Tunnels of dia 5.8 M by shield TBM, 17 M below ground level & construction of 4 underground stations by Cut & Cover method. Length of the tunnels is 8028 M
The project involves the construction of Mumbai metro line (Package-MM3-CBS-UGC 03) with a total length of 5.1 Km including 5 underground stations between Mumbai Central Station and Worli, and a Twin tunnel by Shield TBM of dia 5.8 M & length of 3.645 Km.
The project involves Construction of Digras High Level Barrage in Parbhani Dist, Maharashtra. The Height of Barrage is 33.745 M, the Length is 257 M and has 14 Nos Vertical Gates of size 15 M x 11 M. It has storage capacity of 63.85 MM3.
The project involves Construction of main irrigation canal of 33.50 Km and distributary irrigation canal of 15 Km including construction of 2 No’s Tunnels (1.30 Km & 0.4 Km) long in Canal Alignment in Mongra, Chattisharh
Chairman
Managing Director
Director
Director
Soma's team comprises of highly dedicated, motivated and energetic people with diverse experience in Construction Management and a single-minded focus on execution. The spirit of ownership and entrepreneurship drives every team member to raise the bar consistently to deliver complex projects with quality on schedule.
The team is guided by a highly experienced board with over 125 years of collective experience in infrastructure.
© 2020 SOMA. All rights reserved | Design by nxtk